Infrastructure 4D Planning

The City of Melbourne has been undergoing a very large works program to remove 85 existing rail level crossings or roads by means of grade separation. This generally entails construction of grade separated road and rail alignments by means of elevated bridges or trenching and demolition of existing redundant assets.

RASP was engaged to complete 4D Integrated risk review of project by linking the construction schedule at the Noble Park Station. Stakeholder engagement was a key factor in reviewing the traffic flow and construction activites.

Rasp Competitive Advantages

  • 100% privately Indigenous Owned Company
  • National Footprint
  • Knowledge of Vic Standards
  • Inhouse Design and Drafting Services
  • Locally Resourced Employees

Would you like more Information?

Contact us for a copy of our capability profile & case studies on previous projects.

Get in Touch